Delay in Possession of Flat F-119, I had done a booking for an Flat(F-119/Ground Floor) in TDI Sama
Complain ID : CC31382 90
- State : Uttar Pradesh
- City : Agra
- Address: TDI City Fatehabad Road, Agra
I had done a booking for an Flat(F-119/Ground Floor) in TDI Samarth through Ridge View Developers on 12/03/15, I would like to raise a complaint against the builder for following reasons -
1. At the time of booking I was told that I would be getting a possession of my flat within 8 months of signing of builder buyer agreement, My agreement was signed on 12/03/2015 However as of current status the building is nowhere near completion.
Despite repeated follow up meetings,and phone calls with you on Possession of flat, but still not getting satisfactory response from GHI Team,
This is causing me a lot of financial turmoil as I have already paid a sum of 80% of flat cost, I am required to pay an EMI of 17900 INR each month. All this is causing me a lot of financial burden and mental agony apart from these I am also Paying 8500 INR per month to landlord as rental cost.
as per agreement under cause 10a, in case of delay in possession developers shall pay to the buyer compensation @53.82 inr per sq mtr. as my flat having 154.214 per sq mtr area. seeking your promt support on this matter.
Related complaints
-
Parking Area entry gate width is too small to enter any big carManish Ranjan / Real Estate / November 3, 2018 / Greater Noida / Uttar PradeshI have been given a car parking area in basement. There are two pillars which is the entry gate for entering my parking area and width between these two pillars is approx 6 feet 10 inch. Parking Width After the pillar is more and appropriate. But man...
-
Bluemoon Homes Project Rajnagar ext. Ghaziabad Fraud in Flat (D001) booking and cheating of Rs. 5100HARENDRA SINGH RAWAT / Real Estate / October 9, 2018 / Ghaziabad / Uttar PradeshL.R. Infrahomes India Pvt. Ltd. - Bluemoon Homes Project Rajnagar ext. Ghaziabad made fraud in booking of Flat D001, Ground Floor and cheated Rs. 51000.00 from complainant Prof. Harendra Singh Rawat
-
Posession of flat in Ridge Residency, Today Homes, Sector 135, Noida, delayed by 1 yearShashank Kumar / Real Estate / April 15, 2018 / Noida / Uttar PradeshWe booked the flat in Jan 2016 and it was promised that by Dec 2016 I will get the possesion. When we asked it was told that by Feb,2017 starting they will start giving possesion. In the month of May mail came from Builder that possesion has been sta...
-
Posession of flat in Ridge Residency, Today Homes, Sector 135, Noida, delayed by 3 yearsVijeta Bhatia / Real Estate / December 7, 2017 / Noida / Uttar PradeshWe booked the flat in 2012 with Ridge Residency, Sec 135, Noida (TODAY HOMES)and till date sending reminders to them, after making all payments to them, in a hope to get the final possession of our dream home. All the more paying huge rent… I am very...
-
Delay in possession, booked a expandable prime floor in Uppal Chaddha Group Wave CityKundan singh negi / Real Estate / June 11, 2017 / Ghaziabad / Uttar PradeshI booked a expandable prime floor in Uppal Chaddha Group Wave City in November 2011. I have already paid 30% of the cost of this property {800000 approx} they have initially given me booking in Sec 2 to a floor even where the possession is not in the...
-
Builder, Primrose Infratech Possession delayed by 3 YearsManish / Real Estate / February 8, 2017 / Greater Noida / Uttar PradeshI purchased a property in GNoida in Aug 2012 for which I was supposed to get the possession in Feb 2016 (Last Year). Now, we are in Feb 2017, the current status of the project is not good and now what builder is giving a new date of June 2019. I woul...