Delay in Possession of Flat F-119, I had done a booking for an Flat(F-119/Ground Floor) in TDI Sama

Complain ID : CCN031382   26  

Real Estate Complaint Date: January 17, 2019
Modified date: February 7, 2019
Dear Sir,

I had done a booking for an Flat(F-119/Ground Floor) in TDI Samarth through Ridge View Developers on 12/03/15, I would like to raise a complaint against the builder for following reasons -

1. At the time of booking I was told that I would be getting a possession of my flat within 8 months of signing of builder buyer agreement, My agreement was signed on 12/03/2015 However as of current status the building is nowhere near completion.

Despite repeated follow up meetings,and phone calls with you on Possession of flat, but still not getting satisfactory response from GHI Team,

This is causing me a lot of financial turmoil as I have already paid a sum of 80% of flat cost, I am required to pay an EMI of 17900 INR each month. All this is causing me a lot of financial burden and mental agony apart from these I am also Paying 8500 INR per month to landlord as rental cost.

as per agreement under cause 10a, in case of delay in possession developers shall pay to the buyer compensation @53.82 inr per sq mtr. as my flat having 154.214 per sq mtr area. seeking your promt support on this matter.
Complaint Against : Ridge View Developers Pvt LTD. TDI City Fatehabad Road Agra

Share Now Ask Question Reply Now Contact Submit Complaint

Related complaints

Complaints

    Service issue | Complaint | Query | Feedback | Suggestion | Reply

    Write your Consumer Complaints at forum, talk to members having similar complaints. Consumer Court, Consumer Complaint, Help to file Consumer Complaint Court, Address of Consumer Courts, Complaint against mobile phone service Online Consumer Complaint, Complaint against government department How to trap a bribe seeker Complaint.