In the month of May mail came from Builder that possesion has been started and demand letter has been sent to do the complete payment. We did the complete payment without delay. It is stated in the demand letter that from the date of payment possesion will given within 90 days. Infact I went in month of May to check my flat possesion of tower L. It was not in a condition to get delivered in three months but still they did false promise.
After 4 months when my parents went to see the flat, flat was in same condition. Not even a 1% improvement was done. Even after so many calls and emails I never got a single reply. In fact Managers have unprofessional behavior of not replying to client emails or messages, phone calls.
Its been more than one year and I am not getting the status of my flat. I should get the return interest amount at the rate of 18% for the duration which Today Homes failed to deliver.
I am uploading condition of flat in month of May,2017 and Sept,2017. I do not understand why they do false promise at the time of payment. I need to know my possesion date as I am paying huge rent and interest too.
Related complaints
-
Posession of flat in Ridge Residency, Today Homes, Sector 135, Noida, delayed by 3 yearsVijeta Bhatia / Real Estate / December 7, 2017 / Noida / Uttar PradeshWe booked the flat in 2012 with Ridge Residency, Sec 135, Noida (TODAY HOMES)and till date sending reminders to them, after making all payments to them, in a hope to get the final possession of our dream home. All the more paying huge rent… I am very...
-
Delay in possession, booked a expandable prime floor in Uppal Chaddha Group Wave CityKundan singh negi / Real Estate / June 11, 2017 / Ghaziabad / Uttar PradeshI booked a expandable prime floor in Uppal Chaddha Group Wave City in November 2011. I have already paid 30% of the cost of this property {800000 approx} they have initially given me booking in Sec 2 to a floor even where the possession is not in the...
-
Builder, Primrose Infratech Possession delayed by 3 YearsManish / Real Estate / February 8, 2017 / Greater Noida / Uttar PradeshI purchased a property in GNoida in Aug 2012 for which I was supposed to get the possession in Feb 2016 (Last Year). Now, we are in Feb 2017, the current status of the project is not good and now what builder is giving a new date of June 2019. I woul...
-
Complaint against Company Investor Clinic for not providing NOC regarding Fund transfersanjeev agarwal / Real Estate / August 29, 2016 / Ghaziabad / Uttar PradeshDear all, This is with reference to company Investor Clinic for not providing the NOC regarding the Fund transfer from One Property to Other . I have to provide this NOC to Aznara for fund transfer but i am not getting proper reply for them & cas...
-
Lied & provided incorrect information and cheated, ABA Corp ManagementDeepak Jeswani / Real Estate / July 25, 2016 / Greater Noida / Uttar PradeshDear Cherry County and ABA Corp Management Myself Deepak Kumar Jeswani, having flat A2 2002, which was sold to me (End of 2014 year) with wrong information by Investor Clinic and I was told that this flat no. is not top floor and after making 10% pay...
-
Salary is not given a real estate company named Alfatech Realtors, greater noidaAparana / Real Estate / July 13, 2016 / Noida / Uttar PradeshSir/mam I am working in a real estate company named alfatech realtors,greater noida since last 4 months. I appointed as a back office executive in that company at the salary 12000 per month. but my head who has appointed me they said as joining I am ...