Delay in the Construction of the Apartment in Orris Aster Court Premier
Complain ID : CCN021342 36 Complaint's Reply
Real Estate
Complaint Date: July 26, 2016
Modified date: August 16, 2016
I booked the Apartment in Orris Aster Court Premier, Sector-85, Gurgaon Haryana in September 2011. Builder was supposed to hand over the apartment in 36 months. I have paid 95 % of the amount by Sep 2013. However even after 58 months passed builder has not given the possession of the apartment and there is no hope that builder will provide the possession of apartment even in next 12 months. I need my money back from the builder along with panel interest on that.
Related complaints
-
Booked a 2BHK flat in "Aspen Heights" at Bhiwadi but builder has not delivered the flatBabli Manral / Real Estate February 28, 2024 / North East Delhi / DelhiDear Sir, I am writing to file a complaint against VVA Developers Pvt. Ltd. regarding the non-delivery of the flat as per the agreed upon terms and co...
-
Shop bought with exaggerated price due to false promise of High RentRamya Shetty / Real Estate December 18, 2023 / Mangalore / KarnatakaI am Ramya Shetty from Mangalore, Karnataka, Residing in Kuwait as NRI. I availed vacation in the last year April 2022. and was searching for Commerci...
-
HSVP to refund excess amount paidJAGDEEP SINGH BUDHWAR / Real Estate November 24, 2023 / Rohtak / Haryana1. As a responsible citizen the Complainant on being intimated that additional Enhancement Charges are applicable on Plot No 1021P, Sector 4 Ext, Roht...
-
Not refunding Security DepositHemant Lakhotia / Real Estate November 9, 2023 / Gurgaon / HaryanaLandlord promised to refund security deposit on 7th Nov(the 7th day of the month after leaving the rented apartment), but didn't. Upon asking when wil...
-
HSVP - Refund Of Excess Amount PaidJagdeep Singh Budhwar / Real Estate October 5, 2023 / Rohtak / Haryana1. As a responsible citizen the Complainant on being intimated that additional Enhancement Charges are applicable on Plot No 1021P, Sector 4 Ext, Roht...
-
Refund IssueAnonymous / Real Estate April 15, 2023 /Hi I was looking for a rented apartment in thane and no broker followed up and called me multiple times to take a membership to find house immediately...
Complaints
DELAY IN THE CONSTRUCTION OF THE APARTMENT IN ORRIS ASTER COURT PREMIER by Navin Nath:
(4 of 5)
May please let me know how will you take up the issue with the Builder Orris Infrastructure Private Limited.