Regarding lack of commited amenities
Complain ID : CCN027784 25
Real Estate Complaint
Complaint Date: July 3, 2017
- State : Maharashtra
- City : Palghar
- Address: B/402, Parasnath Nagari, Bldg No.4, Sector 8, Umroli (E). Palghar 401404
Hello Sir/Madam,
Myself Milind Zemse residing at Parasnath Nagari B/402, Bldg No.4, Sector 8, Umroli (E) Palghar 401404.
I had booked the flat on Feb 2014, after getting continuous followups I got the possession of the flat on March 2016. But, some must required amenities has not given us.
It has almost 17 months now still, lift facility has not activated. Even, electricity meter has not been placed. And now, some local contractor (yashodhan) who had build this building is asking to pay electricity bill of Rs. 500 p.m.
Whenever, I take followup regarding lift and electricity meter. I get flying answers that, it will get done soon. I don't know when it will get this solved.
It is now very difficult here to stay with the family as I have small baby and aged parents who cannot use staircase all the time.
It is my humble request, could you please help me?
Regards,
Milind Zemse
Myself Milind Zemse residing at Parasnath Nagari B/402, Bldg No.4, Sector 8, Umroli (E) Palghar 401404.
I had booked the flat on Feb 2014, after getting continuous followups I got the possession of the flat on March 2016. But, some must required amenities has not given us.
It has almost 17 months now still, lift facility has not activated. Even, electricity meter has not been placed. And now, some local contractor (yashodhan) who had build this building is asking to pay electricity bill of Rs. 500 p.m.
Whenever, I take followup regarding lift and electricity meter. I get flying answers that, it will get done soon. I don't know when it will get this solved.
It is now very difficult here to stay with the family as I have small baby and aged parents who cannot use staircase all the time.
It is my humble request, could you please help me?
Regards,
Milind Zemse
Related complaints
-
Delay of 1.5years for possessionAnkur / Real Estate Complaint May 4, 2017 / Pune / Maharashtrahi, This is put on this forum to get guidance as in how can i get the possession of my premises in life Republic Township in Pune which is built by Ko... -
Complaint for Toilet- flat no A-103 Mantra Nighoje ChakanSandeep Kamble / Real Estate Complaint March 30, 2017 / Pune / Maharashtraon 7th Jan 2017 we visited the site and checked our flats there is mistake from builder they putted indian toilet in my flat , when i was booked that ... -
Disha Direct Marketing Services — No registration after taking full payment, reso villa cottageSantosh Ambavkar / Real Estate Complaint February 8, 2017 / Thane / MaharashtraNo registration after taking full payment, reso villa cottage I santosh ambavkar (Owner of cottage no.7) have made 100% payment for this project of di... -
FRAUD CONSTRUCTION CLOSE, Balaji developers Balaji Vision CityAnup / Real Estate Complaint February 8, 2017 / Pune / MaharashtraBalaji developers launched his Balaji Vision City project in Wai, Dist Satara, Maharashtra in 2014. By paying 7Lakhs booking amount through RTGS trans... -
Work unsatisfied, Bolsom 8 in phase1 because of this Enkay Garden managment groupSalma kazi / Real Estate Complaint February 8, 2017 / Panvel / MaharashtraDear All,I gone so frustrate after bought flat no 2,Bolsom 8 in phase1 because of this Enkay Garden managment group. Let me come to point i was compla... -
Harassment by Disha Direct Pvt Ltd not giving propertySalil Shringarpure / Real Estate Complaint January 26, 2017 / Thane / MaharashtraDisha Direct started illicit practices by undue demands and if the demands are not fulfilled they have started to block property documents, I already ...
Complaints
Service issue | Complaint | Query | Feedback | Suggestion | Reply