Effizent Seele Pvt Ltd - Unauthorised GST Suvidha Center License Sales     Rs 5000 not refunded by Friends Car Bazaar, Ambala City     Demanding Extra money from the promised one     Extra meter reading     FAKE Loan , FRAUD COMPANY prerna finserv company     Asking for Money     Wrong product delivered and all fake email ids and mobile numbers are given. We are not able to retu     Terminate bitween medical leave, mently torcher,     My electricity bill comes too much please help me I have visit many time electricity bored office     Order and Payment issue with Jio mart and PayTM  

Delay in Home possession and verify GST paid is correct

Consumer Complaint ID : CCNO34986   9

Consumer Complaint  Post date : February 17, 2021
  • Region :  Maharashtra
  • City :  Thane
  • Address: Room 2 House No 1722, Near Shrikant Jim Ghansoli Gaon Navi Mumbai Mob: 8828284860

Complainant Against:
Prayag builders and developers,
Omkar arcade shop no 17,18
plot no 24 secn15/A
New Panvel 410206

Builder Name: Pradeep Krushna Bhopi
Project Registration No. P52000004381


Subject: Delay in the handover of property and getting compensation along with bank interest, and verify GST amount paid is correct, towards Flat 204, A-wing, second floor in building no 1 of phase-I in your project named Prayag City phase I, situated at survey no 100/5/B Vihighar, Tal Panvel Dist Raigad

Respected Sir / Madam,
This is a reference to the registered agreement for sale dated 27/12/2017 executed between Prayag builders and Shivani Chalge, Amol Khandagale, With the reference to RERA No P52000004381. As per RERA, the property delivery date was 31st DEC 2019 whereas after the year, till the date we are waiting for the possession.

As per the payment term/scheduled agreed upon in the said agreement we have paid a timely amount to the builder as below

Amount paid Details
Particulars Amount Paid (Rs.)
Amount paid through PNB (To builder) 2963520
MSEB (To builder) 20000
Maintenance (To builder) 25800
Global sales tax (To builder) 291514
Bank Interest (To bank) 648853.59
Total Amount 3949687.59


Whereas we have paid Rs. 648853.59 as an interest to the bank and also we are continuously paying monthly EMIs and monthly house rent. Hence it becomes very difficult to run the family.
When we are getting late for the payment to the builder, they charge heavy dues as 18% on the amount, the same rule should be applicable for both. (I have attached notice as proof for the same)

We also want to know that GST amount paid by us is really paid to Govt. or not. Is it the case they have taken an extra amount under the name of GST. As per our knowledge govt had lowered the GST rates whereas we have paid by 12% and 8%.

Please understand the concern and help in getting home possession as early as possible, compensation, and bank interest amount till the date of possession.

Submit Complaints

Review Date :
Reviewed Item : Consumer Complaint
Author Rating : 5
Vote
Result 0 votes

Share Now Ask Question Reply Now Contact Submit Complaint

Consumer Complaint

    Complaint | Query | Feedback | Suggestion | Reply